Below is our typical
building process. To view the building process for properties at Summerset
at Frick Park, click here.
| Step |
Customer Perspective |
Builder Perspective |
Time Frame |
| Pre-Sale Agreement |
| 1 |
Select lot; sign lot reservation agreement. Place
lot reservation deposit. |
|
Varies |
| 2 |
House design finalized, specifications (including exterior
selections) and option list finalized. |
10 to 90 days |
| 3 |
Sign Agreement of Sale.
Amount due at signing:
5% of base price plus 100% of options or 10% of the total price. |
1 day |
| Building Permit Application |
| 4 |
Commence interior selection process |
Cross sections, details and elevations are added to the plans. |
1 to 2 weeks |
| 5 |
|
Building permit application |
1 to 2 weeks |
| Construction Process |
| 6 |
|
Building Permit received. Construction begins – property surveyed
and staked, excavation, foundation formed and poured, block work. |
5 weeks |
| 7 |
Majority of interior selections must be complete due to the need
to be able to locate rough-ins for plumbing and HVAC |
House framed; stairs, windows and doors installed; roof installed. |
6 weeks |
| 8 |
|
Rough in for plumbing and HVAC commenced. |
2 weeks |
| 9 |
Electrical walk through – select locations for
electrical openings and structured wiring. |
1 day |
| 10 |
|
Installation of electrical and structured wiring; plumbing and HVAC
rough in completed |
1 week |
| 11 |
|
Exterior finish, insulation, drywall, paint, steps and driveway. |
3 to 4 weeks |
| 12 |
|
Finish work – flooring, cabinets, doors, lighting and plumbing
fixtures. |
4 to 6 weeks |
| 13 |
|
Punch list work completed for interior and exterior |
1 week |
| 14 |
Walk through and closing |
1 day |